Canada’s commitment to reduce methane emissions in the upstream oil and gas sector by 40% to 45% below 2012 levels by 2025 led to federal regulations whose first requirements came into force in 2020, focused on emissions limits and mandatory equipment inspection and repair. Building on that foundation and on Canada’s policy commitment to cut oil and gas methane emissions by at least 75% below 2012 levels by 2030, the federal government has now finalized amendments to these regulations.
Final Amendments
The final amendments were announced on December 12, 2025, and published in the Canada Gazette, Part II, on December 31, 2025 (SOR/2025-280). They apply across Canada’s onshore upstream oil and gas sector for facilities that extract, process, or transport hydrocarbons. The previous 60,000 m³/year gas volume threshold has been removed, and offshore facilities are now excluded, as they are covered by separate offshore petroleum framework regulations. The regulations are now structured as two compliance pathways:
- Part 1 sets prescriptive requirements.
- Part 2 offers an optional performance-based alternative for facilities using a continuous emission monitoring system, provided facility emission intensity stays below prescribed reference standards (0.2% for production, 0.05% for processing, 0.11% for transmission facilities).
Note: the amendments do not require each facility to hit a specific reduction figure; the 75% target is a sector-wide policy objective that the rules are designed to help meet.
Updates from the 2023 Proposal
The core of the December 2023 proposal remained intact. The key changes made in response to consultation include:
- Timing: Initial compliance shifted from Jan 1 2027 to Jan 1, 2028, with full sector application still in Jan 1, 2030.
- Facility classification: Gas-liquid separators were removed from the Type 1 definition, moving many well sites to the less frequent Type 2 inspection schedule, and inactive facilities were exempted from comprehensive inspections.
- New venting relief: The exception for low-producing oil facilities (up to 12,000 m³/year of venting) did not exist in the proposal.
- Equipment flexibility: The proposal required a pilot flame, automatic ignition, and flame failure detection together; the final rules require only flame failure detection or weekly visual inspections, plus a relight capability. The 85% minimum efficiency for catalytic oxidizers was replaced with operation per manufacturer recommendations.
- Part 2 redesign: The performance-based pathway moved from a zero-based alarm threshold to facility emission intensity reference standards with electronic alerts, addressing concerns about current monitoring technology.
Key Emissions Affected
- Venting emissions: Hydrocarbon gas venting is prohibited, with limited exceptions for emergencies, planned maintenance or depressurization, gas streams that cannot sustain stable destruction, and avoiding interruptions of gas supply to the public. A new exception allows low-producing oil facilities that began operating before 2028 (≤600 m³ crude oil/year) to vent up to 12,000 m³ of gas per year.
- Emissions associated with destruction of hydrocarbon gas: Combustion systems must achieve at least 98% carbon conversion efficiency, with either automatic flame failure detection or weekly visual inspections. Any non-emergency destruction must be supported by an engineering study, reassessed annually, concluding that using the gas for heat or energy is not feasible.
- Fugitive emissions: A risk-based inspection regime requires quarterly inspections at Type 1 facilities and annual inspections at all other active facilities, plus monthly instrument-based screening during site visits and one annual inspection by an independent third-party auditor. Repair timelines scale with leak size:
- 24 hours for leaks of 100 kg/h or more
- 7 days for leaks between 10–100 kg/h
- 30 days for leaks between 1–10 kg/h
- 90 days for leaks under 1 kg/h.
Important Dates
- January 1, 2028
- The fugitive emissions detection and repair program takes effect for all facilities.
- The venting and destruction requirements apply to facilities beginning operations on or after this date.
- The Part 2 performance-based pathway becomes available. This replaces the 2027 start date stated in the 2023 proposal.
- January 1, 2030
- The venting and destruction requirements extend to all existing facilities, those that began operating before January 1, 2028.
The government estimates the amendments will deliver 304 Mt CO2e in cumulative GHG reductions from 2028 to 2040 at a cost of $14.6 billion (roughly $48 per tonne).
What’s Next
Publication of the final amendments triggers a reassessment of the equivalency agreements the federal government renewed with Alberta, British Columbia, and Saskatchewan under which the federal rules are currently stood down in those provinces.
All three are now working toward updated equivalency arrangements based on the final rules. Alberta is furthest along, having reached an agreement-in-principle with Ottawa in March 2026. Whether the federal amendments ultimately apply directly in these provinces will depend on whether the provincial regimes are found to deliver equivalent outcomes.